Similkameen Subdivision

This 38 service 18 lot duplex subdivision was completed by LNB in the summer of 2011.  Despite extensive ground water impeding into our excavations, limited information on existing utilities and maintaining access for local traffic our crew managed to complete the project in record time.  Work on this project also included the following.

  • 36 live sewer service installations
  • Install 350 meters of 10” diameter storm main
  • 10 catch basins
  • 4 dry wells
  • 8” hot tap into an existing water main with a major road crossing on Hwy 3 completed and paved in one day.
  • 550m of 200mm watermain