PEACE RIVER COAL PROJECT (PHASE TWO)
DETAILED INFORMATION
DATE:
2014 – 2014
LOCATION:
Tumbler Ridge, BC
CLIENT:
Anglo-American
VALUE:
$10.8 Million
PROJECT SNAPSHOT
Infracon was contracted by Anglo-American to complete the water management portion of their Roman Pit Expansion. Time lines were very tight on the project and there were significant liquidated damages for late completion and a bonus structure for completing early. Infracon achieved early completion bonuses by mobilizing a large fleet of equipment, including excavators (Cat 390, JD 800, 3 x 470’s, 4x 350, 1 x 200), dozers (3 x 850K, 2 x D8T), rock trucks (7 x 40 Tonne, 4 x 30 Tonne) a JD824K loader, a JD 772 grader and multiple packers and support equipment.
KEY HIGHLIGHTS
- 80,000 m2 of clearing and grubbing
- 80,000 m3 of drilling and blasting to fill and disposal
- 25,000 m3 of riprap production and placement
- 3 km of collection ditches
- 200,000 m3 of overburden excavation
- Construction of two detention ponds, including 45,000 m2 of bituminous geo-membrane liner