Loading...

DETAILED INFORMATION

DATE:

2018 – 2019

LOCATION:

Fort St. James, BC

CLIENT:

David Nairne and Associates

VALUE:

$2.8 Million

PROJECT SNAPSHOT

Infracon Construction Inc. (Infracon) was contracted David Nairne and Associates to complete a 22 lot subdivision including: site and lot grading, storm, sanitary, watermain, culverts, lift station and final paving. Infracon successfully completed this project by leveraging our relationships with local employees, subcontractors and suppliers.

KEY HIGHLIGHTS

  • Installation of 340Lm of sanitary and sewer main
  • Installation of 300Lm of watermain
  • Installation and tie in of 42 services
  • 6,400m3 of road gravel
  • 8,600m2 of asphalt paving
  • Lift station install
  • Supply and install 180Lm of 500mm culverts

ARE YOU READY TO START YOUR NEXT PROJECT WITH US?