City of Kamloops – Sewage Treatment Plant Pre-Load

In December of 2010 LNB hauled, placed and packed approximately 90,000 cubic meters of structural fill into the Kamloops sewage treatment plant. The objective of this project was to pre-load a large area for a new section of sewage treatment plant. Our qualified asbestos team was involved to remove asbestos pipe and asbestos contaminated dirt. The project was completed in 1.5 months, well ahead of schedule.

  • Removal of asbestos pipe and asbestos contaminated dirt.
  • Installation of 25 meters of 900mm diameter pipe
  • Flow control valve set in a 30,000 lb concrete vault