Mount Merrick Project

Detailed Information

DATE:

2020 – 2021

LOCATION:

56 km Sakunka FSR, B.C.

CLIENT:

Black Diamond Limited Partnership (+West Moberly First Nation)

VALUE:

$4.5 Million

PROJECT Snapshot

Completed full turnkey project, including geotechnical investigation, engineered design, and earthworks construction of a 4(Ha) footprint multi-use pad. Infracon utilized multiple dozers and excavators, 30T & 40T rock trucks, tractor and disc, packers and a 4,000-gallon water truck to complete the work.  Import material was hauled to site from an off-site gravel pit with multiple highway dump trucks. The project was completed on-time with zero lost-time incidents.

94BF6128-761D-4956-A592-381A1800E30D

Key Highlights

  • Performed geotechnical investigation and engineered design.
  • Cut and filled.
  • Executed and completed perimeter ditching.
  • Imported structural fill from off-site.
  • Installation of multiple layers of geotextile, due to poor ground conditions.
  • Supplied and installed culverts.
  • Supplied and installed perimeter chain link fence.
  • Twenty per cent of employees were Indigenous.

WESTPRO INFRASTRUCTURE

“Infracon successfully completed a project for Westpro Infrastructure in Fort McMurray, Alberta in the summer 2013. I found their management team to be committed to the completion of a top quality project. Infracon personnel were knowledgeable, hard-working and professional in all aspects of their work. Infracon simply performed a miracle – mobilized in one week notice and was able to complete earth and civil works on time in spite of the record-breaking wettest summer in 30 years.”