Lornex Pit Dewatering Pipeline Project

Detailed Information

DATE:

2017

LOCATION:

Logan Lake, B.C.

CLIENT:

Tech Highland Valley Copper Partnership

VALUE:

$1.2 Million

PROJECT Snapshot

Lower Nicola Site Services (LNSS), a partnership between Infracon and the Lower Nicola Indian Band Development Corporation, was contracted to construct a 3.6-km high-density polyethylene and carbon steel pipeline to connect the booster station in the Lornex Pit to the million-gallon tanks at the operating level of the mine. LNSS also constructed the haul road crossings and haul road detours.

Lornex Pit 2

Key Highlights

  • 1,200 M 14” carbon steel piping.
  • 1,600 M 18” DR11 HDPE piping
  • 880 M 14” DR 17 HDPE piping.
  • 500 M 8” DR09 HDPE piping.
  • 33 per cent of employees were Indigenous.
  • 876.5 Indigenous man-hours dedicated to project.

WESTPRO INFRASTRUCTURE

“Infracon successfully completed a project for Westpro Infrastructure in Fort McMurray, Alberta in the summer 2013. I found their management team to be committed to the completion of a top quality project. Infracon personnel were knowledgeable, hard-working and professional in all aspects of their work. Infracon simply performed a miracle – mobilized in one week notice and was able to complete earth and civil works on time in spite of the record-breaking wettest summer in 30 years.”