Domtar Pulp and Paper Mill – Treated Effluent Line

During later winter 2011, LNB excavated and installed the main effluent line for Domtar Pulp & Paper mill. This project had a very strict schedule and extremely sensitive environmental policies due to the proximity to the Thompson River. The project was completed two weeks before the Spring run-off thanks to the hard work and 24 hour commitment of our crews. LNB’s efficiency and quality of work resulted in additional work from the client.

  • 1100m of 1050mm high density poly effluent line
  • Replanting of over 14,000 trees crafted from the native species
  • 24 Hour work schedule